QC Online Quiz


Following quiz provides Multiple Choice Questions (MCQs) related to QC Framework. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - What are the potential subsequent states of a "Fixed" defect? (Select two.)

  1. Closed

  2. Reopened

  3. Complete

  4. New

  5. Reviewed

A - (1) and (2) only

B - (2) and (3) Only

C - (1) (2) and (4) Only

D - All the Above

Answer : A

Explanation

Closed and Reopened are the subsequent states of the defects with Fixed status.

Answer : B

Explanation

The Test list comprises of tests that may be included in the tester's next run.

Q 3 - Which integrations for HP Application Lifecycle Management are supported by the Free HP ALM Mylyn Connector? (Select two.)

  1. Microsoft TFS connector

  2. Bugzilla

  3. Collabnet connector

  4. CVS

  5. Rational CiearQuest

A - (1) and (2) only

B - (2) and (4) only

C - (3) and (5) only

D - (3) and (2) only

Answer : B

Explanation

Bugzilla and CVS integrations are supported by the Free HP ALM Mylyn Connector.

Answer : A

Explanation

priority refers to how soon the defect needs to be fixed.

Q 5 - In which tab can you define traceability links ?

A - Impact Analysis

B - Test Coverage

C - Relationships

D - Risk

Answer : A

Explanation

Relationships tab can you define traceability links.

Q 6 - Your test set includes two automated tests: Open Order and Update Order. How can you configure the Execution Flow to ensure the Update Order test will only run after the Open Order test completes successfully?

A - Define an Execution Condition where Open Order must Finish before Update Order starts.

B - Define Update Order as a dependent test to Open Order.

C - Define an Execution Condition where Open Order must Pass before Update Order starts.

D - Define an Execution Condition where Update Order must Pass before Open Order starts.

Answer : C

Explanation

Define an Execution Condition where Open Order must Pass before Update Order starts.

Q 7 - A _________ is a view of a ALM window with the settings you apply to it.

A - Personal view

B - My view

C - Favorite view

D - User view

Answer : C

Explanation

Favorite view is a view of a ALM window with the settings you apply to it.

Q 8 - A _________ requirement is a requirement belonging to a type that represents requirements that are children of analysis requirements and at a lower level in the requirements tree hierarchy.

A - Analysis

B - Assessment

C - Policy

D - Test

Answer : B

Explanation

A Assessment requirement is a requirement belonging to a type that represents requirements that are children of analysis requirements and at a lower level in the requirements tree hierarchy.

Answer : A

Explanation

The Requirement module field Direct Cover Status means the current status of the requirement.

Q 10 - ALM assigns the image a unique file name with a _______ Extension.

A - .jpeg

B - .gif

C - .doc

D - .jpg

Answer : D

Explanation

The Image with a .jpg extension.