Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - Which of the following submodule of Plant Maintenance is used to maintain high availability of the technical system?

A - Inspection

B - Repair

C - Preventive Maintenance

D - Breakdown Maintenance

Answer : C

Explanation

Inspection

Inspection is done to check the actual condition of a technical system.

Preventive Maintenance

Preventive maintenance is used to maintain high availability of the technical system. It includes maintenance planning and work scheduling activities for technical objects.

Repair

Repair involves all measures that can be performed to restore the ideal condition.

Q 2 - In Preventive Maintenance, a multiple counter plan do not have their own maintenance strategy and have the cycle sets. They contain a combination of time-based and performance-based cycles?

A - True

B - False

Answer : A

Q 3 - Which of the following plan can be created without a maintenance strategy and is used for performance based maintenance?

A - Single Cycle Plan

B - Strategy Plan

C - Multiple Counter plan

D - Maintenance plan for service procurement

Answer : C

Explanation

A multiple counter plan can be created without a maintenance strategy and is used for performance based maintenance. In the multiple counter plan you create maintenance cycles and allocate counters of equipment or functional locations with different dimensions to them.

Q 4 - In which of the component, capacity of work centers are shown in graphical manner and you can use new planning tree for displaying capacity view of planning board?

A - MEB

B - Log Book

C - Outline agreement

D - Service Contract

Answer : A

Explanation

Using MEB in SAP Plant Maintenance, you can easily manage the maintenance planning consists of work packages. The capacity of work centers are shown in graphical manner and you can use new planning tree for displaying capacity view of planning board.

Q 5 - In an Organization, Which of the following factor doesn’t affect work place safety?

A - Task Category

B - Technical specifications of the system

C - Organization within the maintenance department

D - Bill of Material

Answer : D

Q 6 - In Refurbishment process, to move the material to Warehouse which of the following movement type is created?

A - Movement type 101

B - Movement type 102

C - Movement type 103

D - Movement type 104

Answer : A

Q 8 - Which of the following shows an invalid warranty and negative checks are shown for Warranty claim results?

A - 00

B - 03

C - 01

D - 02

Answer : B

Explanation

  • 00 shows a valid warranty and positive check result are shown.
  • 03 shows an invalid warranty and negative check result are shown.
  • 01 shows no warranty check possible since required measuring point is missing in the warranty claim.
  • 02 shows no warranty check possible since required measurement document is missing in the system.

Q 9 - When you create a maintenance strategy plan for a Printer to be performed after 1 million copies, it is example of?

A - Time based

B - Performance Based

C - Both of these

Answer : B

Q 10 - In Plant Maintenance, you can make a location field as mandatory in IW31 T-Code?

A - True

B - False

Answer : A

Explanation

Yes, in T-code: IW31 → Location → Location Tab (Mandatory)