- SAP PP Tutorial
- SAP PP - Home
- SAP PP - Introduction
- SAP PP - Common Tables
- SAP PP - Organization Structure
- Integration with Other Modules
- SAP PP - Master Data
- SAP PP - Bill of Materials
- SAP PP - Work Center
- SAP PP - Routing
- SAP PP - Demand Management
- SAP PP - Creating PIR
- Material Requirement Planning
- SAP PP - MRP List
- SAP PP - Long Term Planning
- SAP PP - Production Orders
- SAP PP - Production Order Change
- Production Order Confirmation
- Canceling Production Order
- SAP PP - Capacity Planning
- SAP PP - Capacity Leveling
- SAP PP - Goods Receipt
- SAP PP - Stock Overview
- SAP PP - Goods Issue
- SAP PP - Goods Issue Reversal
- SAP PP - Lean Manufacturing
- SAP PP - Reports
- SAP PP - Material Document List
- Stock of Multiple Materials
- List in Bill of Material
- SAP PP Useful Resources
- SAP PP - Questions Answers
- SAP PP - Quick Guide
- SAP PP - Useful Resources
- SAP PP - Discussion
- Selected Reading
- UPSC IAS Exams Notes
- Developer's Best Practices
- Questions and Answers
- Effective Resume Writing
- HR Interview Questions
- Computer Glossary
- Who is Who
SAP PP Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?
Answer : B
Explanation
Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.
In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.
Q 2 - When you create a Material BOM without a Plant is known as?
Answer : C
Q 3 - Which of the following T-code can be used to change Routing in PP?
Answer : B
Q 4 - Which of the following movement type is used for Goods Receipt in to Warehouse?
Answer : A
Q 5 - Which of the following movement type is used to transfer Posting to storage location?
Answer : D
Q 6 - Using T-Code CO01, you can create a Production order without referring planned order?
Answer : A
Explanation
Q 7 - Simulative planning is performed only for long duration and it is not performed for short term and when there is no time restriction?
Answer : B
Q 8 - When material is produced as per Production order and goods is placed at storage location, which of the following is correct?
A - Stock Quantity is increased and movement type is 103
B - Stock Quantity remain same and movement type is 103
Answer : C
Explanation
Good receipt is performed when material is produced as per Production order and goods is placed at storage location. The stock quantity is increased and movement type 101 is entered.
Q 9 - A Storage location is defined as location where materials are stored in plant?
Answer : A
Q 10 - Which of the following Transaction can be used confirm a Production Order and for Goods movement?
Answer : C
Explanation
To confirm Production Order, use T-code: CO15
You can perform following activities −
- Generate confirmation document
- Consume raw materials or semi-finished goods
- Good receipt of finished goods or semi-finished goods